How we build one floor

Every slab goes through the same nine stages. Step through them to see what happens on site and what we check before moving on.

props
Section through one bayStage 1 of 9
Stage 1

Set props and primary beams

Props stand on the floor below at the planned spacing. Their heads are adjusted so the primary beams sit at the right height for the slab soffit.

What we checkProp spacing and plumb, and that the slab below can carry them.

How long a floor takes

We plan each floor around a two-week cycle with a five-person crew, then adjust it to the slab area, the frame system and how fast concrete and crane time can be booked.

Estimate the schedule for your building

What we need from the developer

A floor cycle only holds if these are ready on time. We agree them at the site visit.

  • Approved drawings

    Current architectural and structural sets, with revisions issued before the stage they affect.

  • Concrete supply

    A batching plant booked for each pour date, with the specified class and slump.

  • Crane or pump time

    Lifting for formwork and rebar, and a pump or bucket slot for the pour.

  • Your supervisor

    Someone from your side at the pre-pour inspection to sign the checklist with us.