Every slab goes through the same nine stages. Step through them to see what happens on site and what we check before moving on.
Set props and primary beams
Props stand on the floor below at the planned spacing. Their heads are adjusted so the primary beams sit at the right height for the slab soffit.
How long a floor takes
We plan each floor around a two-week cycle with a five-person crew, then adjust it to the slab area, the frame system and how fast concrete and crane time can be booked.
What we need from the developer
A floor cycle only holds if these are ready on time. We agree them at the site visit.
Approved drawings
Current architectural and structural sets, with revisions issued before the stage they affect.
Concrete supply
A batching plant booked for each pour date, with the specified class and slump.
Crane or pump time
Lifting for formwork and rebar, and a pump or bucket slot for the pour.
Your supervisor
Someone from your side at the pre-pour inspection to sign the checklist with us.