Beambrace / Estimator
Estimate your frame
Quantities and a floor-by-floor schedule from four numbers. Use it to compare systems early; your real price comes from your drawings.
Frame duration, foundation to roof slab
≈ 20 weeks
13 working days per floor × 9 floors, beam and slab frame
4,050 m²total floor area
1,069–1,361 m³concrete
150–191 treinforcement
720 m²formwork contact per floor
Floor 9
Floor 8
Floor 7
Floor 6
Floor 5
Floor 4
Floor 3
Floor 2
Floor 1
0 wk5 wk10 wk15 wk20 wk
Indicative figures from typical ratios for each system, shown as a range of ±12%. Structural design and site conditions change them.
How the estimate works
Each system has typical ratios: concrete per m² of floor including columns and beams, kilograms of rebar per m³ of concrete, formwork contact area per m² and crew effort per m². Days per floor never drop below seven, because concrete needs time before the next floor can be loaded.